GOLD MINING AND PROCESSING UPDATE

by Montpellier

Horizon Minerals Limited (ASX: HRZ) (“Horizon” or “the Company”) is pleased to provide an update on the development of the Phillips Find (“Phillips Find”) and Boorara (“Boorara”) Gold Projects.

HIGHLIGHTS

Phillips Find

  1. Toll processing of the second stockpile of ore from the Phillips Find JV with BML (BML Ventures Pty Ltd) completed
  2. 18,676 dry tonnes of ore at 1.97g/t Au and 95.5% metallurgical recovery delivered 1,132.2oz sold at an average price of $5,140/oz, generating ~$5.8M in revenue to the Phillips Find JV
  3. First free cashflow distribution from the project achieved, generating ~$1.5M in net cashflow directly to Horizon
  4. An additional 87,000t of ore will be Toll Treated at the Greenfields Mill in August 2025, including 27,000t of ore from Boorara, to complete the Toll Milling Agreement with FMR
  5. The remaining 70,000t of ore from Phillips Find will be processed at Focus Minerals Limited’s Three Mile Hill processing plant in September/October 2025 to complete this first phase of mining at Phillips Find

Click here to read full announcement

Find out more about Horizon Minerals at: HorizonMinerals.com.au